Adif considers the Madrid-Seville line repaired after a month of interruption because of the Adamuz accident | Economy | EUROtoday

The infrastructure supervisor Adif has accomplished the restore work on the not too long ago rebuilt part of the Madrid-Seville high-speed line the place the accident on January 18 in Adamuz passed off. The entity signifies that, as soon as the checks carried out are accomplished, the monitor is on the market to the railway firms to hold out the checks they deem acceptable in an effort to resume business service. For its half, the railway operator Renfe is already testing stated part this afternoon, as sources from the Ministry of Transport verify to this newspaper. The goal is to reopen the road in its entirety this Tuesday, after it was lower off between Villanueva de Córdoba and Córdoba because of the injury brought on by the collision of an Iryo practice and a Renfe Alvia.

The Minister of Transport, Óscar Puente, introduced this morning Adif’s intention to reopen this route “tomorrow or the day after.” The announcement got here on the finish of the presentation ceremony of the España Crece fund. When requested by the media, Puente indicated that work is being accomplished to revive visitors “as soon as possible.”

The public operator Renfe has put AVE service tickets on sale once more beginning this Tuesday with out interruptions to the journey. Their rivals Iryo and Ouigo even have the provide of seats open for journey tomorrow. Until now, customers who’ve opted for the practice to journey between Madrid and Seville, with Renfe as the one choice, needed to change from the practice to a bus to cowl the journey between Villanueva de Córdoba and Córdoba. It was the choice provided by the general public operator instead transportation plan, in response to the aforementioned line lower.

The journey between each cities by AVE and bus nonetheless takes 5 hours and seven minutes this Monday, whereas tomorrow’s Tuesday journeys have instances that vary between 2 hours and 39 minutes and three hours and eight minutes, with out interruptions between the Puertollano and Córdoba stations. The better of these schedules can be provided by Ouigo and Iryo.

The Ministry of Transportation provided a primary estimate of the completion of the reconstruction works on the Adamuz part, and the start-up of visitors, for February 2. However, judicial authorization for the beginning of labor didn’t arrive till January 28, as soon as technicians from the Railway Accident Investigation Commission (CIAF) and members of the Civil Guard concluded the gathering of proof on the scene of the accident that price the lives of 46 folks. As of this final date, Óscar Puente anticipated the repairs to be accomplished inside roughly ten days. But the tough climate in latest weeks in Andalusia has made work with heavy equipment tough, as soon as once more inflicting failure to adjust to the deliberate schedule.

Transport has resorted to the emergency mechanism contemplated within the Public Sector Contracts Law (article 120) to fee the works. This is the method already used on the finish of 2024 for the restore of a number of infrastructures within the Valencian Community affected by dana. In emergency instances, public procurement is deliberate with out the standard processes of an odd competitors.

https://elpais.com/economia/2026-02-16/puente-preve-que-la-linea-madrid-sevilla-abra-manana-o-pasado-tras-un-mes-de-corte-por-el-siniestro-de-adamuz.html